Client:Tallahassee Orthopedic Clinic
Location :Tallahassee, FL
Budget :$14,248,649
Architect :Elliot Marshall Innes, PA
Completion :March 2020

Tallahassee Orthopedic Clinic

With the growth of Tallahassee and the advancement of technology, the Tallahassee Orthopedic Clinic (TOC) is in need of a new facility to keep with their expanding practice. Ajax will serve as TOC’s construction manager and work hand-in-hand to design and deliver an approximately 30,000 SF facility that will house space for x-rays, casting, exam rooms, physical therapy and offices. TOC’s two story building will be designed and constructed to allow flexibility of space to accommodate future growth, technology advancements and changing needs.

CURRENT STATUS (as of 4/5/19)

March was a productive month. The construction trailer has been built out, and now has functioning temporary power. The Welaunee Rd west construction entrance has been completed. This entrance is only intended to be used after a heavy rain event. The underground storm drains are 95% complete, while the building footers are 75% complete. Elevator pits are expected to be complete during the first week of April, and all of the ground face block will be delivered the second week of April. The project completion date has been adjusted to 03/25/20 to reflect final completion. Substantial completion is currently tracking for 02/20/20. DEP and COT have had multiple site visits which we have passed. No safety violations/issues.