Client:Sumter County Board of Commissioners
Location :Bushnell, FL
Budget :$19,988,758
Architect :Clemons, Rutherford & Associates, Inc.
Completion :March 2021

Sumter County Jail Expansion

The Sumter Jail will consist of a one-story, two level tilt panel housing pod building with a total gross square footage of 38,662.  The building will have an inmate capacity of 256.  Modular cells are included on all four (4) sides of the building at two (2) levels with a security mesh protection at the mezzanine level. There is a control room in the middle for observation and controlling the inmate population. The maintenance access is divided into a quadrant and includes a corridor for each housing pod. An enclosed fenced walkway extends from an existing building to connect to the new housing pod. Electrical renovations to the existing Bravo facility will also be included.

CURRENT STATUS (as of 4/7/2020)

Throughout the month of March; MEP tilt panel rough-in has been completed and concrete tilt walls has been formed & poured. Tilt Wall panel forms has been stripped and 7-Day breaks have resulted in an average over 75% strength. Crane has been delivered and the road has been completed in the anticipation of erecting in the month of April. Welding of preliminary steel clips has begun as installation of steel & decking is forthcoming.