Client:Pinellas County School Board
Location :Largo, Florida
Budget :$7,364,995
Architect :Holmes Architects
Completion :December 2018

Pinellas County Schools Bardmoor Elementary School Renovations

This project consists of all renovation work done in five (5) phases to the existing occupied Building 1. It will include selective demolition, new interior walls, doors and hardware, casework, new electrical, LED lighting, low voltage systems, mechanical system modifications, complete fire protection system, restroom and plumbing additions/modifications, new ceilings, clerestory window installations, interior paint, new ceilings, and related accessories. The scope also includes minor modifications to various low voltage systems in existing Building 3.

CURRENT STATUS (as of 12/5/18)

Phase 5
Phase 5 life safety and substantial completion inspections were held on November 14th, 2018. Ajax is working on the Phase 5 punchlist.