Client:GA Board of Regents
Location :Atlanta, Georgia
Budget :$10,139,969
Architect :Pond & Company
Completion :April 2019

Georgia Institute of Technology Campus Safety Facility

This new 30,000 square foot facility will allow the campus to replace obsolete police facilities, consolidate the units into one location, and modernize the police functions. The proposed building will house all units and departments of the Georgia Tech Police Department, along with all of their storage needs. The project will require a significant amount of secure outdoor structured parking for patrol vehicles, utility trailers, and specialty vehicles. While many of the program elements are typical to an office building, such as offices and conference rooms, there are several unique elements specific to the function of a Police Department. Some of these elements include an Emergency Operations Center, K9 facilities, locker rooms, a Forensic Lab, an Armory and an exterior vehicular sally-port for secure movement of persons in custody.

This project is pursuing a Georgia Peach Green Building Certification. ga-peach-logo-web

 

CURRENT STATUS (as of 4/5/19)

Pervious paving is now installed. South plaza hardscape is completed. Sidewalks and North plaza hardscape is being installed. Asphalt drive has been installed at the basement drive and the binder coat has been installed at the south parking lot drive. Light poles have been installed at the parking lot. Exterior building signage and the monument signage is installed. Interior building signage is installed. All finishes within building are complete including polished concrete floors. Fire extinguishers cabinets with fire extinguishers are installed. All lockers are installed. Final elevator inspection has been conducted. Building commissioning is ongoing. GT has now installed their network equipment and the building is now on GT server. Site landscaping walls are being installed. Hardscape work is ongoing. Pervious paving will be installed in a week. Casework is almost complete. Reception area millwork is almost complete with the exception of the ballistic door. All doors and hardware installation is complete with the exception of 5 leaves. Glass and glazing work is all complete. Drywall and ceilings installation is completed. Painting work is all complete. Lockers are being installed. Roofing work is 97% completed. MEP and fire sprinkler work is about 95% complete. Electrical commissioning is completed and HVAC commissioning will begin mid-march. All low voltage work is almost complete. GT will be installing their network equipment sometime this week, after which this project will be on GT server and all controls work will be completed then. Final elevator inspection is scheduled for March 7th.