Client:Florida State University
Location :Tallahassee, Florida
Budget :$59,000,000
Architect :Bohlin Cywinski Jackson Architects
Completion :July 2019

Florida State University, Earth, Ocean, and Atmospheric Sciences Building

The facility will provide space for the Earth, Ocean, and Atmospheric Sciences Department, which has been newly formed by merging the former departments of geology, oceanography, and meteorology. The project aims to provide state of the art accommodations for the department’s classrooms, teaching labs, research labs, and offices. It will also seek to promote the use of the exterior areas including reinforcement of the building’s location at a major gateway to the campus. As the home for the University’s environmental sciences programs, this project will strive to support the protection of environmental resources and promote a healthy indoor environment.

The building is anticipated to be approximately 130,000 gross square feet. Along with its construction, the scope of services is expected to include site utilities and site amenities, and may include construction of elements required to support the project’s location in the NW Science Quadrant. At the University’s discretion, the selected construction manager may be contracted to construct/include renovation of an existing adjacent building, should it be deemed more favorable to house portions of the program scope in the adjacent facility. Furthermore, should funding for a second building phase become available, the University may at its discretion, choose to extend the contract to incorporate the second phase. The design is being developed by Bohlin Cywinski Jackson Architects based in Pittsburgh, PA.

Visit the Webcam. Enjoy a Panoramic View. Also, check out the 3D Model.

CURRENT STATUS: (4/5/19)

During the month of  March, MEPF overhead and in-wall rough-in, curtain wall installation, brick work, and roofing were again the main activities. Significant progress was made in the Mechanical Penthouse with boiler and water heater installation, louvers, piping, and electrical work. Electricians ran conduit and pulled wire on several levels and continued work in Electrical Rooms and began installing lighting on Level 02. Plumbing rough-in is mostly complete up to Level 07. Gas piping and equipment is being installed in the Mechanical Penthouse. Curtainwall is nearly complete on the West elevation and crews will be moving to the North Elevation next month. Brick on the North elevation is complete as is the NE Bay Window Precast. Interior metal framing was 90% completed for all levels and drywall hanging continued up to Level 06 and 07 along with Painting on several levels.